Real projects, real results. See how Du Toit's Heavy Lifting has solved complex transport challenges for South Africa's leading companies.

Anglo Mining Corp

85-Ton Excavator: Cape Town to Lusaka

The Challenge

Transport a Komatsu PC850 excavator 1,800km across two borders within a 48-hour window to meet mine commissioning deadline.

Our Solution

Deployed a 6-axle heavy-duty lowbed with dual escort vehicles. Pre-arranged border permits for Zimbabwe and Zambia transit. 24-hour relay driver system.

85 tons
Load Weight
1,800 km
Distance
48 hours
Delivery Time
2
Borders Crossed

"Du Toit's delivered exactly when they said they would. The permit coordination across two countries was seamless."

Johan van der Merwe, Project Manager

Eskom Projects

120-Ton Transformer Relocation

The Challenge

Move a 120-ton power transformer from Durban port to a new substation in Mpumalanga through narrow rural roads with weight-restricted bridges.

Our Solution

Used an 8-axle hydraulic lowbed with load-spreading capabilities. Conducted full route survey with bridge assessments. Arranged night moves to minimise traffic disruption.

120 tons
Load Weight
580 km
Distance
3 conducted
Route Surveys
On schedule
Delivery

"Their route survey identified a bridge limitation that would have caused a major delay. Professional from start to finish."

Sarah Nkosi, Logistics Coordinator

Windforce Energy

Wind Farm Blade Transport — 73m Blades

The Challenge

Transport twenty-four 73-metre wind turbine blades from Coega port to a wind farm near Cradock over narrow mountain passes.

Our Solution

Specialised blade trailers with steerable rear axles. Full escort convoy with advance route clearing. Night transport schedule for mountain passes.

73 metres
Blade Length
24 units
Total Blades
310 km
Distance
Zero incidents
Safety Record

"The only company we trust with our turbine components. Their blade transport expertise is unmatched in South Africa."

Peter Botha, Operations Director

Kumba Iron Ore

Mine Fleet Relocation — 12 Machines

The Challenge

Relocate an entire fleet of 12 mining machines from a closing pit to a new operation 400km away within a 2-week shutdown window.

Our Solution

Deployed 8 lowbed units simultaneously with a dedicated project coordinator. Staggered loading schedule to maximise efficiency. GPS tracking dashboard for client monitoring.

12 units
Total Machines
650+ tons
Combined Weight
11 days
Completed In
15% under
Budget Savings

"They moved our entire fleet 3 days ahead of schedule and under budget. Exceptional project management."

Thabo Molefe, Mine Manager